PDF icon Environment (PDF - 1.33MB)

Environment

Key indicatorsreasonable assurance

  • AngloGold Ashanti formally adopted ISO 14001 as the standard for the group’s environmental management system during 2005. The group has set itself the target of achieving certification of its operating mines by the end of 2006. The following operations currently have ISO 14001 certification: Cerro Vanguardia in Argentina; AngloGold Ashanti Minera??o and Serra Grande in Brazil; Bibiani and Iduapriem in Ghana; and Geita in Tanzania. Further details may be found under review 2005 of this report.
  • All the South African operations have approved Environmental Management Programmes (EMPs) in place. These EMPs are required in terms of South African environmental and mining legislation and were reviewed during the year as part of the company’s application for the conversion of its mining rights in terms of the Minerals and Petroleum Resources Development Act (MPRDA). AngloGold Ashanti was the first gold mining company to receive all of its ‘new order’ mining rights in South Africa.
  • All operations have set aside financial resources for the rehabilitation and eventual closure of operations. As at the end of 2005, the estimated liability amounted to $337.7 million (2004: $350.1 million). A detailed breakdown by country/operation may be found under review 2005 of this report.
  • Environmental incidents of actual or potential significance are reported to the Board Committee on Safety, Health and Sustainable Development. 24 incidents of varying degrees of severity were reported in 2005. Further details may be found under review 2005 of this report.
  • AngloGold Ashanti is committed to complying with all applicable legislation and regulations pertaining to the environment. At Obuasi in Ghana, the Environmental Protection Agency raised a number of concerns about the failure of the operation to achieve water quality discharge standards. An internal review of the operation has identified a series of remedial actions to address this situation.
  • The following key performance indicators are reported for AngloGold Ashanti in 2005.*
    • Total cyanide usage was 31,939,528 kg. A table listing cyanide usage per country/operation may be found under review 2005 of this report.*
    • Total water use was 78,458,736 m3. A breakdown of water usage by country/operation may be found under review 2005 of this report.*
    • Total direct energy use was 29,213,073 GJ. (See review 2005 of this report for a breakdown of consumption by country/operation.)*

* Note that only information from the South African operations was assured by PwC.